ANDRAVIDA AIRPORT

ANDRAVIDA AIRPORTANDRAVIDA AIRPORT

Space frame design of the airport terminal building, covering a total area of 5,700m2, with only 5 internal columns. Various other reinforced concrete buildings (Fire service - Airport controller - Warehouse- Belts etc.). Landscaping of surrounding area (road construction, parcking facilities, rainwater sewer etc).

  • Client: MINISTRY OF TRANSPORTS (CIVIL AVIATION AUTHORITY)
  • Design Stages: Preliminary, Scheme and Detailed Design, Tender Documents
  • Budget (Structural): 3,785,000 €
  • Design Period: 20/05/2002 – 15/12/2003
  • Project State: Not out to tender yet
  • Architectural Design: SYNTHESI & EREVNA Ltd G. ALBANIS - N. FINTANAKIS ARCHITECTS CONSULTANT ENGINEERS
  • E/M Design: INSTA CONSULTANTS ENGINEERS K. GALANIS Bros